One week to get as much done on the MZ12 as I possibly can.
Goals:
- All electric cabling, cleaned, tested and installed
 - All brake lines installed
 - All engine coolant lines and radiator installed
 - All underhood electric components cleaned and installed
 - All underdash electrical components tested and installed, including fuse boxes
 - Underdash AC and Heater units rebuilt and installed
 - Side mirrors installed
 - Roof header installed
 - Carpet and rear seats installed
 - Window trim installed
 - Windscreen wipers, horn and washers work
 - Driveshaft installed
 - Install exhaust
 - Fuel tank rebuilt and installed
 - Fill engine with oil
 
Stretch Goals:
- Engine turns over for first time
 - Bumper bars rebuilt and installed
 - Windscreens, front and rear installed
 - Rear lights installed
 - Dashboard completely rebuilt and installed
 - External trim installed
 
Days Plan:
- Cleaning Day - Soda blast everything, and paint any brackets or miscellaneous pieces.
 - Wiring day - Check and clean all the wiring, rebuild the engine harness with new connectors
 - Fetch day - Get as many necessary spare parts from the MZ11 as I can
 
	